- Incomplete MEP Design at Project Start: A recurring challenge is the lack of a fully developed and spatially coordinated MEP design at the outset of the project. This gap forces project teams into a reactive mode, where design and installation must be sequenced on-the-fly. This approach is not only inefficient but also necessitates additional time for resolving design clashes and advancing detailed technical design.
- Communication Breakdowns Between Design and Installation Teams: Another critical issue is the ineffective communication between the design and installation teams. Problems often arise when site supervisors are not kept informed of the design challenges and decisions. Conversely, the design team may be unaware of the practical difficulties encountered by the site team. This disconnect is exacerbated by issues like inaccurate or unverified modelling of architectural and structural elements, leading to frequent rework. Such scenarios erode trust in the coordination process and compromise the quality of work on site.
</aside>
<aside>
<img src="https://s3-us-west-2.amazonaws.com/secure.notion-static.com/d6831872-e8fb-4fc5-9536-50db7b9d9822/empty.png" alt="https://s3-us-west-2.amazonaws.com/secure.notion-static.com/d6831872-e8fb-4fc5-9536-50db7b9d9822/empty.png" width="40px" /> Recommendations:
- If the First and the most important step in spatial coordination is the volume strategy, the second is the confirmation of sizes of all the equipment and systems to be installed
- In our experience, the most important factor is to have a process in place and someone who has the authority to enforce the process.
- The most effective approach involves the Technical Services Manager (TSM) leading the Building Information Modelling (BIM) process. The TSM's has the authority to implement and enforce the necessary processes.
- Success in digital construction and BIM also hinges on having a broad understanding of the relevant technology and processes. This 'horizontal' knowledge is key to effective implementation.
- Effective clash management requires the active participation of the installation(site) team in meetings. The presence and engagement of the site supervisor are essential for facilitating clear communication between the design and site teams, ensuring that issues are promptly addressed and resolved.
Jarek Wityk on LinkedIn: #innovatewithme #doorjambclearance #bim #buildingservices #mep
Key Takeaways:
Emphasise the importance of training and strong leadership for successful BIM implementation.
</aside>
<aside>
<img src="https://s3-us-west-2.amazonaws.com/secure.notion-static.com/8df95945-0479-497e-a150-8710961a5012/empty.png" alt="https://s3-us-west-2.amazonaws.com/secure.notion-static.com/8df95945-0479-497e-a150-8710961a5012/empty.png" width="40px" /> Successes:
2024-01-08_Coordination - Clash management.pdf